The revised schedule for the Main Road Rehabilitation now has the end of Phase 2, the current Phase, listed as being June 2013 – it is already running several months late. Funding has now been obtained for Phase 3 – Kalk Bay Harbour to Clovelly Road and Atlantic Road to Casa Labia.
Whist the concept design has been completed, a contractor has yet to be appointed. Phase 3 is anticipated to be a 3-year project. It is hoped that a contractor could be on site to commence with Phase 3 in September 2013. However, the City’s procurement and appeal process could delay the commencement.